Your Bathroom Renovation Timeline: What to Expect From Day 1 to Final Handover
- De Witt Bathrooms
- 5 days ago
- 3 min read
If you’re planning a bathroom renovation, one of the first questions you’ll ask is: ‘How long is this going to take?’ It’s a fair question — and the honest answer is that timelines depend on scope, access, and what we find once we open up the space.
Below is the practical, step-by-step timeline we use to keep projects moving smoothly. It’s written for South African homes and real-world conditions — not a perfect-world brochure.
1) Before we start: planning and decisions
A smooth renovation starts before the first tile comes off the wall. The more decisions you lock in early, the fewer delays you’ll face later.

Confirm the layout (shower position, vanity size, door swing, window clearance).
Choose your finishes (tiles, grout colour, taps, sanitaryware) early.
Confirm electrical points (lighting, extractor fan, heated towel rail if applicable).
Agree on access times and where rubble will be removed.
2) Day 1–2: protection and demolition
We protect adjacent areas, isolate services where needed, and then remove the old bathroom carefully. Demolition is fast — but it must be controlled to avoid damage to surrounding finishes.
3) Day 2–4: plumbing and ‘what’s behind the walls’
This is where timelines can change — because older bathrooms often hide surprises. The key is to address them properly, not patch them.
On every De Witt Bathrooms project, we replace ALL old pipes with new copper as standard. That’s not an optional extra — it’s how we protect the long-term reliability of the installation.

4) Day 3–5: electrical and ventilation
Once the walls are open, electrical work is done at the right stage — not as an afterthought. Good lighting and proper ventilation make a bathroom feel premium and help prevent moisture problems over time.
5) Day 4–6: waterproofing (non-negotiable)
Waterproofing is mandatory on every project without exception. It’s one of the most important steps in the entire renovation — and it must be done properly before tiling begins.

If you remember one thing: tiles are not waterproofing. Waterproofing is a dedicated system underneath the tiles.
6) Day 6–10: tiling and finishes
Tiling is where the bathroom starts looking like a bathroom again — but it’s also where workmanship shows. Straight lines, clean falls to the drain, neat corners, and consistent grout spacing are what separate a ‘quick job’ from a professional finish.
7) Final days: fit-off, sealing, testing and handover
The last stage is fitting sanitaryware and accessories, sealing correctly, testing plumbing and drainage, and doing a proper clean-down. We don’t rush handover — we want you to walk into a bathroom that’s ready to use and built to last.
FAQ-style questions we hear all the time
Here are a few quick answers to common questions homeowners ask us before we start:
Will you need to switch off my water? — Usually yes for short periods during plumbing changes, and we plan it to minimise disruption.
Can I use another bathroom during the renovation? — Yes, and we’ll help you plan access and dust control so the rest of the home stays comfortable.
What causes the biggest delays? — Late product decisions, out-of-stock items, and hidden issues behind walls. Early planning reduces all three.
Do you reuse existing pipes? — No. We replace ALL old pipes with new copper as standard on every project.
Is waterproofing optional if I’m using ‘good tiles’? — No. Waterproofing is mandatory on every project without exception.